"The most persuasive economic impact exhibit is not the one with the biggest numbers. It is the one whose numbers hold up when the county board, the intervenors, and the Commission's staff each take their turn asking where they came from."
The Requirement

What a Siting Application Has to Show

In Wisconsin, any non-utility solar project of 100 MW or more, and any utility project above the Certificate of Authority cost threshold, needs a Certificate of Public Convenience and Necessity from the Public Service Commission. The Commission's Application Filing Requirements for solar generation direct the applicant to describe the project's effects on local government budgets, estimate the revenue to each host community in taxes, shared revenue, or payments in lieu of taxes, describe other community benefits such as local employment, and provide information on the direct, indirect, and induced state and local economic impacts during and after construction. The wind requirements carry a parallel local-government-impacts section, and battery storage is addressed within hybrid solar applications.

Ohio's Power Siting Board rules require the same content in more detail — construction and operating payroll, employment and the share drawn from the region, and tax revenue by jurisdiction. New York's Article VIII process requires a socioeconomic-effects exhibit, and Michigan's PA 233 siting process requires a showing of public benefits including local tax revenue, landowner payments, and local jobs. The exhibit is a filing requirement everywhere in the region and, increasingly, the document that gets quoted at every local hearing.

Six Figures Every Hearing Quotes

The Headline Results

  • Construction jobs — full-time-equivalent years with peak-month headcount, for the host county and the state
  • Long-term jobs — operations and maintenance staffing plus the jobs supported by O&M spending and landowner income
  • Economic output and labor income — one-time construction and annual operations, direct, indirect, and induced, never summed across phases
  • Annual local revenue — utility aid or PILOT payments to the county and to each town or village, under the statute that actually applies
  • Lifetime local revenue — over the project life, including one-time charges and any negotiated agreements
  • Landowner payments and local workforce share — documented, tested, and presented as a range
What Makes It Defensible

The Supporting Record

Every exhibit ships with an assumptions register that records each input, its source, and its date; a sensitivity table on the two or three assumptions that drive results — the resident labor share, the local materials share, and the fiscal rate; and a short review of the peer-reviewed evidence on property values and community effects, so the applicant is not caught flat when the question comes.

Modeling files are retained for reproducibility and for potential third-party review. The report follows the section order that Commission staff and intervenors have seen in prior dockets, so it reads as a familiar exhibit rather than a novel argument.

Sources: PSC of Wisconsin, Application Filing Requirements — Solar Generation (Sept. 2025), §§3.2, 6.1; Wind Generation (Aug. 2026); Ohio Adm. Code 4906-4-06(D); 16 NYCRR Part 1101; Michigan Public Act 233 of 2023.

How project spending becomes regional economic impact Project Budget Bill of goods from the EPC Modules · Inverters Trackers · Transformers Site Work · BOS Aggregate · concrete · electrical Construction Labor Resident · non-resident Soft Costs Engineering · legal · finance Land & O&M Leases · maintenance · staffing Regional Capture Documented local share of each line ≈ 0% local Leakage — margins only Meaningful local share By supplier location Split by residency Per-diem spending for crews By provider location Only in-region providers count Household & O&M income Resident landowners; actual budgets Reported Impacts County and state, side by side Construction (one-time) Jobs · income · value added · output Operations (annual + NPV) Direct · indirect · induced Fiscal (by jurisdiction) Utility aid · PILOT · one-time charges Assumptions & sensitivity Register · ranges · retained files RPC / LPP I-O model Regional purchase / local purchase coefficients applied line by line Imported equipment treated as leakage

Figure: Analysis-by-parts — how each line of a project budget becomes a regional impact, with imported equipment treated as leakage rather than local manufacturing.

The Analytical Framework

Eight Principles That Make the Numbers Hold

Utility-scale energy projects are unlike generic construction: most of the capital is manufactured equipment made elsewhere, most of the construction crew travels, and operations are thin on staff but durable on income. A methodology that ignores those facts overstates local impacts and gets taken apart at the hearing. These principles follow IMPLAN's published guidance for solar construction and operations and the Lawrence Berkeley National Laboratory parameter sets.

01Analysis-by-parts, not a single-sector shockThe capital budget is decomposed into a bill of goods; each line is assigned its documented regional purchase share.
02Imported equipment is leakageModules, inverters, trackers, and transformers carry a local share at or near zero unless in-region sourcing is documented.
03Two geographies, leakage made explicitHost county and state modeled in parallel; the difference is itself a reportable finding.
04Honest labor accountingConstruction jobs in FTE-years tied to the schedule, never presented as permanent; traveling crews enter only through per-diem spending; the resident share is tested as a range.
05Operations from actual flowsO&M budgets, site staffing, and landowner lease income — not generation revenue pushed through a capital-intensive sector's default multipliers.
06Gross and net, both shownAgricultural output foregone on the footprint is netted visibly; displaced activity is discussed rather than ignored.
07The fiscal mechanism that actually appliesWisconsin utility aid per megawatt by jurisdiction, Ohio's qualified-energy-project PILOT, Michigan's host community agreement — verified at drafting, not assumed.
08Built for the recordAssumptions register, sensitivity ranges, retained modeling files, and citations to published guidance and peer-reviewed literature.
+Tertiary effects, where the evidence supports themFiscal capacity for host communities, farm-household income stabilization, workforce spillovers, and renewable supply as a site-selection asset — analyzed quantitatively where possible and qualitatively otherwise.
Wisconsin Specifics

How Host Communities Are Actually Paid

Wisconsin exempts utility-scale generation from local general property tax. Host counties and municipalities are compensated instead through statutory utility aid, calculated per megawatt of installed capacity. The schedule below is what a Wisconsin exhibit must reproduce, jurisdiction by jurisdiction, and what every town board will ask about first.

ComponentAmountWho receives itAuthority
Production-capacity payment (solar, wind)$2,000 per MW per yearTwo-thirds county, one-third town (reversed for a city or village host)Wis. Stat. § 79.04
Alternative-energy incentive payment$1,500 per MW per year to eachCounty and host municipality separately§ 79.04, as increased by 2023 Wisconsin Act 19
Combined annual aid (solar, wind)$5,000 per MW per yearRoughly $2,833 county and $2,167 town per MW in a town-hosted project; per-capita caps apply to the non-incentive components—
Battery energy storage aid$1,000 per MW of storage capacity, beginning with 2027 paymentsSame county-municipality split; utility-owned systems of 1 MW or more2025 Wisconsin Act 163
Agricultural conversion charge (one-time)Varies by county; 2025 statewide average about $283 per acre for conversions over 30 acresSplit evenly between county and municipalityWis. Stat. § 74.485
Negotiated commitmentsProject-specific (joint development agreements, school payments, road agreements)As agreedContract

Illustration: a 150 MW solar project in a single town generates about $750,000 per year in utility aid — roughly $425,000 to the county and $325,000 to the town — or $22.5 million over a thirty-year life, before any one-time charges or negotiated payments. Rates verified with the Wisconsin Department of Revenue at drafting; figures above reflect statute as of September 2026.

How an Exhibit Is Prepared

From Scoping Call to Filed Exhibit

1

Scope and Data

Project size, host jurisdictions, filing date, and offtake confirmed on one call; a structured data request follows authorization.

2

Study-Area Models

County and state input-output models built with a project-specific bill of goods and documented regional purchase coefficients.

3

Construction and Operations

One-time construction impacts and annual operations impacts estimated separately, with resident-labor and local-content sensitivities.

4

Fiscal Schedule

Utility aid, PILOT, or production-tax payments computed per jurisdiction under the statute that applies, with one-time charges and negotiated commitments.

5

Exhibit and Record

Report formatted to the application, executive summary for community audiences, assumptions register, and retained modeling files for the docket.

Practical Applications

Where This Analysis Is Used

Siting Application Exhibits

The economic and fiscal impact section of a CPCN, OPSB, Article VIII, or PA 233 application, formatted to the filing requirements and coordinated with counsel and the environmental consultant.

Host Community Briefings

Per-community fiscal one-pagers and town-board presentation support that translate aggregate dollars into service and levy terms residents recognize.

Docket Support and Testimony

Responses to Commission staff and intervenor data requests, supplemental town-level tables, rebuttal analysis, and expert testimony grounded in the retained record.

Joint Development and Community Benefit Agreements

Valuation of proposed payments, school and road commitments, and local-hire pledges so both the developer and the host community negotiate from the same numbers.

Independent Review for Communities

For counties, towns, and intervenors: an independent reading of an applicant's exhibit against the same standards, so decision-makers know which numbers to rely on.

Portfolio and Siting Analytics

Repeatable exhibits across a developer's regional pipeline, and county-level screening of prospective sites on economic and fiscal criteria.

Why This Approach

Transparent Where It Counts

Most economic impact reports filed with siting applications run total project cost through a construction sector multiplier and present the result as local jobs. That is the approach intervenors have learned to challenge. This framework differs in four ways.

Local Share Is Documented, Not Defaulted

Each budget line carries a regional purchase share drawn from the EPC's sourcing plan or a stated benchmark, disclosed in the assumptions register. Reviewers can see exactly why imported modules do not create local manufacturing jobs.

Jobs Are Counted the Way They Occur

Construction employment is reported in full-time-equivalent years with peak-month headcount, resident and non-resident crews are separated, and operations staffing reflects actual O&M plans — never a rolled-up "jobs created" total.

The Fiscal Story Is Jurisdiction-Specific

Utility aid by county and by town, the one-time conversion charge, school-levy interactions, and any negotiated commitments — expressed per household and relative to the local levy, which is how a town board thinks about it.

The Hard Questions Are Answered in Advance

Property values, farmland loss, construction-period housing demand, and decommissioning are addressed directly with the peer-reviewed evidence, so the exhibit anticipates the hearing rather than reacting to it.

Preparing a Siting Application in Wisconsin or the Great Lakes Region?

DMP Development Analytics offers a standardized economic impact exhibit with fixed scope, fixed turnaround, and a written quote within one business day of a scoping call. We also work with host communities and counties that need an independent reading of an applicant's numbers.

Photo: Solar farm in Wisconsin: Wikideas1, CC0, via Wikimedia Commons.